Casing removal MV Transshelf
Dockwise MV Transshelf will discharge a topside module for the Claire Ridge project (North Sea). Prior to this operation, the (buoyancy) casings have to be lifted from the HTV deck. After arrival, the HTV started bunkering. At the same time, ERP Trading BV started working to disconnect electricity and hydrolic from the casings.
After bunkering ERP Trading BV immediately started with HotWork and after 14hrs operation finished the work, so the MV Transshelf could leave for the Claire Ridge field.